Project | 01
Stellenbosch Square | Development
Project size: 11 300m² / 121 632, 188 sq ft
Tenants: from 45 to 75
Timeline: 18 months
Completed: March 2016
Budget: R60 million
Overview: Upgraded all soft furnishings within passageways, public bathrooms and courtyard. Demolished existing centre building to create large open air piazza. Redesign entry and build added bulk to increase tenancy and redesign parking layout to maximize ratio.
Project | 02
Stellenbosch Square | Rebrand & Refresh
Overview: While the centre was undergoing an extensive face-lift, I was tasked to relook at the brand guide for the centre. This included a new look website, refresh of all marketing material and the launch of the centre on Twitter.
Budget compile and execute
Conceptualize on brand guide and launch
Approve all designs, adverts and press releases
Liaise with media on all advert bookings and press releases
Ensure the smooth coordination of the launch of the centre
Create brand and info packs for potential tenants and suppliers
Report on the campaign to exco team
Skills
Skills
Compile due diligence on availability of land
Source international tenant
Lease agreement conclude
Tenant Liaison
Project coordination
Entry/Beneficial occupation manage
Snag lists
Health & Safety check lists
Project | 03
Building Project | Burger King Cape Gate
Project size: 315m² / 3390,63 sq ft
Tenants: 1
Timeline: 6 months
Completed: May 2017
Budget: R5.5 million, including tenant T/I
Overview: The precinct already offered two national drive-thru's however the centre parking area allowed for a slight reconfiguration which enabled a third outlet to be built, solidifying the node as a convenient shopping destination.
Skills
Manage network with Brokers
Secure new tenants
Budget management
Leasing strategy
Tenant Liaison
Project coordination
Entry/Beneficial occupation manage
Snag lists
Health & Safety check lists
Project | 04
Refurbishment | Laguna Mall
Project size: 17 000m² / 182986 sq ft
Tenants: 70
Timeline: 12 months
Completion: Nov 2018
With the recent acquisition of the centre a focus on the interior and exterior revitalization will take place starting February 2018. This includes new floor tiles, installing modern light fixtures, new ceiling/bulk heads and modern public bathrooms. Included in this project is the line shops interior upgrades which are linked to their lease agreements.
Skills
Project | 05
Parow Valley Apartments | Extension
Project size: 6 000m²
Units: 20
Timeline: 12 months
Completion: Nov 2018
Low income housing project where an additional 20 units is currently being built which will bring the apartment block to a total of 68 units
Implement marketing/sales and PR strategy
Host open days to Real Estate Brokers
Project coordination
Municipal liaison
Skills
Implement marketing/sales and PR strategy
Source national tenant and conclude lease agreement
Project coordination
Municipal liaison
Project | 06
Nandos Drive-thu | Cape Gate Lifestyle Precinct
Project size: 358m²
Tenant: Nandos
Timeline: 06 months
Completion: June 2018
Nando’s Drive Thru building project commenced on 15 January 2018. Handed over on 19 June 2018, the development will further strengthen the trade within the precinct improving the overall shopping experience for all visitors.